Most carriers still route around the Cape of Good Hope on Asia–Europe services. Here’s what that means for planning, and what we’re doing for clients on those lanes.
How much time to add
Plan for 10–14 extra days compared with Suez routings on Asia to North Europe, and a little less into the Mediterranean. Build that into factory cut-offs and launch dates, not just the delivery estimate.
Schedules are also less reliable. Ships that arrive late in Europe leave late for Asia, so a delay on one voyage can ripple into the next booking.
What it does to cost
Longer voyages use more fuel and tie up more ships. That shows up as higher bunker surcharges and, at times, emergency or contingency surcharges. Ask for these to be shown as separate lines so you can see what changes and when.
What we’re doing
We’re holding extra allocation on key lanes and flagging every schedule change as soon as we see it. Coordinators update the expected arrival in your tracking link, so your team works from the same date we do.
Weekly lane updates for clients on Asia–Europe
Sea-air options through Dubai for urgent stock
Earlier cut-off reminders for factories
What you can do
Move forward the orders that matter most, keep a few weeks more safety stock on fast sellers, and talk to your coordinator about splitting urgent lines onto sea-air.