Moving 480-tonne transformers across two ports

Client

Vantor Energy

Industry

Energy

Lane

Houston → Santos

Services

Project cargo, permits

The problem

Two 480-tonne transformers had to reach a substation in Brazil with a fixed energisation date. Road bridges, port cranes and a narrow river window all had to line up.

What we changed

The moves
we made

Month 1

Surveyed the route

Engineers checked 340 km of road and reinforced two culverts.

Month 2

Booked the vessel

A heavy-lift vessel was fixed, with lift plans at both ports.

Month 3

Secured permits

Road, port and customs approvals were handled by one team.

Month 4

Set down

Modular trailers delivered both units onto foundations, three days early.

The result

Heaviest unit

Heaviest unit

480 t

Delivered ahead of schedule

Delivered ahead of schedule

3 days

Damage claims

Damage claims

0

“Three days early and zero damage on our biggest move to date.”

Marcus Bell · Project Director, Vantor Energy

Still buying

on spot?

Send us a year of invoices. We’ll show you what a contracted programme would look like, at no cost.

Still buying

on spot?

Send us a year of invoices. We’ll show you what a contracted programme would look like, at no cost.

Create a free website with Framer, the website builder loved by startups, designers and agencies.