Moving 480-tonne transformers across two ports
Client
Vantor Energy
Industry
Energy
Lane
Houston → Santos
Services
Project cargo, permits
The problem
Two 480-tonne transformers had to reach a substation in Brazil with a fixed energisation date. Road bridges, port cranes and a narrow river window all had to line up.


What we changed
The moves
we made
Month 1
Surveyed the route
Engineers checked 340 km of road and reinforced two culverts.
Month 2
Booked the vessel
A heavy-lift vessel was fixed, with lift plans at both ports.
Month 3
Secured permits
Road, port and customs approvals were handled by one team.
Month 4
Set down
Modular trailers delivered both units onto foundations, three days early.
The result
480 t
3 days
0
“Three days early and zero damage on our biggest move to date.”
Marcus Bell · Project Director, Vantor Energy