A line-down rescue in 31 hours
Client
Kestrel Motors
Industry
Automotive
Lane
Pune → Stuttgart
Services
Air charter, customs
The problem
A fire at a tier-two supplier in Pune left a German assembly line with less than two days of a safety-critical part. Commercial space was full for a week, and every hour of downtime was costing six figures.


What we changed
The moves
we made
Hour 0–2
Took the call
Our recovery desk mapped the part volumes and contacted three alternative suppliers.
Hour 2–8
Sourced capacity
A part charter out of Mumbai was secured, with trucking from Pune under escort.
Hour 8–20
Pre-cleared
German customs entry was filed in advance, with AEO fast-track on arrival.
Hour 20–31
Delivered
Parts reached the line side nine hours before stock ran out.
The result
€2.1M
31 h
0
“When a supplier fire stopped our Pune parts, Tidegate had them in Stuttgart 31 hours later. The line never stopped.”